How to Avoid the Planning Fallacy and Develop More Realistic Project Schedules
November 22, 2019
When it comes to project schedules, some timelines are more optimistic than others – and that can lead to big issues later on. Those who have a hard time estimating durations that are reasonable could be providing more of a “best case” scenario versus what represents a more practical assessment.
It’s a concept called the Planning Fallacy, first proposed by Daniel Kahneman and Amos Tversky in 1979.
So why does this phenomenon occur and how can project managers develop schedules that are more realistic?
First, let’s discuss the planning fallacy concept: A tendency to underestimate how much time is required to complete a task, which, when accumulating over an amount of time with other improperly planned tasks, can lead to an unrealistic project schedule.
There are 4 main reasons why people underestimate their task completion times:
Group Optimism Bias
When a group reviews a challenge, does the group learn from that experience? Often, no. It’s more likely that the group maintains optimistic time predictions, unknowingly or unconsciously, that a unique external event occurred with no chance of that failure happening again. These cognitive biases impact task completion predictions with overly optimistic predictions.
Backward Planning
What we mean is that a project estimated backward from the forecasted end date on the schedule could have an adverse effect on durations. Rather than a realistic duration associated with each task, the duration gets shortened in order to accommodate the overall schedule. Many other elements can suffer as a result, including scope, cost and quality.
Overpromising
There is often a sense by project managers and other team members that nobody understands the project’s timeline better than they themselves do. So, for example, when an outsider to the project is skeptical of the proposed schedule, they might allow their egos to take over, seeing this skepticism as a challenge to their credibility. The unintended consequence of this action is a highly aggressive schedule with numerous shortened durations that the team must now accommodate.
Lack Of Full Team Input
At times, the most dominant voice in the room for planning discussions belongs to a high-level person who has little interest in obtaining input on the project schedule from a variety of team members. This individual will rarely consider all elements of the schedule and will be primarily locked on a particular date or goal that must be reached at all costs. Unfortunately, that person’s optimistic view of the schedule, often results in time management issues.
The good news is that corrective procedures can bring the project back into alignment if a few important steps are taken:
1. Gather Insights From External Data, Not Internal Voices Exclusively
The schedule will typically be better served with a more practical and unbiased outlook if external data from similar tasks or projects are included. How do those past projects’ timelines and outcomes compare to the current project’s schedule? Relying solely on the intuitive predictions of the project’s current participants can be too insulating. Remove this variable and use comparable projects as a true source of validation.
2. Plan For The Unplanned From The Very Beginning
We often hear about post-mortem meetings, in which the team reviews a completed project to dissect what went wrong and what could have been improved upon. While there is still a place for that discussion to occur, consider moving that conversation to the beginning. Start by envisioning an outcome where the project has derailed or completed beyond the timeline projected. What went wrong? Were there certain elements the team had been too optimistic about delivering on a particular date? Were there elements that were outside of the team’s direct control that no one accounted for?
The point of this type of meeting is to get the entire team thinking about the hidden risks in the project schedule given their past experiences, and making the proper adjustments in the schedule now to allow for situations where these variables may present themselves.
3. Designate A Third-Party To Lead Planning Sessions
The fact of the matter is that, try as one might, it’s very hard for a team to create a project schedule in a vacuum without the benefit of an outside perspective. So, in addition to the use of external data from similar projects, we also suggest utilizing a third party to facilitate planning sessions. We call this the “Coach’s Challenge,” to borrow a concept from the National Football League. Much like how a coach will throw a challenge flag onto the field when they disagree with a referee’s call, the third party facilitator can throw a challenge toward any decision made by the group that doesn’t make sense or carries an unnecessary level of risk that hasn’t been thoroughly discussed.
Whether the resolution of the challenge is to stay the course or to revise accordingly based on the facilitator’s thinking, the point is that the Coach’s Challenge slows the process down in a constructive manner at a key point in time. It allows the team to focus on how it arrived at its decision and if it has sufficiently factored in areas of risk that could influence the schedule.
It’s always the hope that data helps people avoid risk. Generally speaking, with risk analysis, the more data at one’s fingertips, the better the analysis can be. One of the best tools is NetRisk™, a module for NetPoint®, which allows one to perform qualitative and quantitative risk analysis.
The system provides an inherent integration with the planning process, enhanced schedule modeling capabilities, and cost functionality. NetRisk™ provides a strategy for identifying and controlling project or program risk, and allows professionals to bring risk management into the future of project planning.
Discover how NetRisk™ can get and keep your next project aligned with a realistic schedule every step of the way by receiving a demo today. Learn more about mitigating the planning fallacy by reading one of our related publications.
Mitigating the Planning Fallacy (Risked Schedules—The New Normal)
In support of this strategy, Dr. Gui introduces GPM schedule risk analysis and provides a demonstrative using NetRisk, download the presentation to learn more.
The Planning Fallacy and Its Effect on Realistic Project Schedules
As a project manager or planner, it’s important to recognize when these psychological effects are impacting your project schedule. The authors, Jeff Valdahl and Shannon Katt, use examples from various projects to show where this challenging planning issue is likely to occur. Identifying where adjustments need to be made at both the task and overall project level is essential in developing a project schedule that is both achievable and reasonable.
Published by AACE® International in Cost Engineering.