Schedule Statistics
NetPoint tracks a number of statistics for each plan, such as the number of activities, types of links, and float distributions.
Steps
- Click Schedule Statistics window will open. from the menu bar. The
- When finished, click the red X in the upper right to close the window.
Notes
Metric | Definition |
Activity Count | The number of activities in the schedule. |
Hammock Count | The number of hammocks in the schedule. |
Link Count | The number of links in the schedule. |
Redundant Link Count | The number of redundant links in the schedule. |
Logic Index | The number of valid links divided by number of activities in the schedule. |
Start Embeds | The number of start embeds in the schedule. |
Finish Embeds | The number of finish embeds in the schedule. |
Start Milestones | The number of start milestones in the schedule. |
Finish Milestones | The number of finish milestones in the schedule. |
Start Milestones | The number of start benchmarks in the schedule. |
Finish Milestones | The number of finish benchmarks in the schedule. |
Zero-gap Links | The number of zero-gap links in the schedule. |
Project Duration in Calendar Periods | The number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) between the project start and project completion, including holidays, non-working periods, and weekends. |
Project Duration in Work Periods | The number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) between the project start and project completion, excluding holidays, non-working periods, and weekends (based on whichever calendar has been selected as default). |
Longest Path in Calendar Periods | The chain of linked objects that lasts the most number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) including holidays, non-working periods, and weekends. |
Longest Path in Work Periods | The chain of linked objects that lasts the most number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) excluding holidays, non-working periods, and weekends. |
Hard-Links Count | The number of hard links in the schedule. |
Soft-Links Count | The number of soft links in the schedule. |
Resource-Links Count | The number of resources links in the schedule. |
External-Links Count | The number of external links in the schedule. |
Contractual-Links Count | The number of contractual links in the schedule. |
Float Distributions | The percentile rank for different float values. |