Once dates and/or durations have been updated on the canvas (i.e. statused), objects must be actualized to complete the update process. Once actualized, the object becomes outlined in blue, and...
Once the data date has been set and a target has been captured, actual dates and durations can be entered (also known as “statusing”). In NetPoint, actual dates and durations...
A data date is an object on the canvas used to represent the date to which the project has been statused. Data dates help provide a clear visual indicator of...
Once a schedule has been created, it may be updated to track and monitor progress. In NetPoint, entering actual dates and durations (also known as “statusing”) is done just like...
NOTE: The full chapter is available with the purchase of the license.
It is said that building a schedule is often more art than science. Imagine then for a moment that...
As objects become linked, they form chains. For any object in a chain, its predecessors are those that are connected by a link that terminates at the given object, and its successors...
NetPoint tracks a number of statistics for each plan, such as the number of activities, types of links, and float distributions.
Steps
Click Schedule > View Statistics… from the menu bar....
NetPoint allows you to divide each window into more than one canvas for the same schedule. This can be useful when you have a large schedule that can’t fit within...
Schedule MD™ is a companion application to NetPoint for analyzing and determining the reliability of schedules. The Schedule IQ™ Score is a rating system based on the Core Traits of a...
Multiple objects may be edited at the same time through the Set Global Properties window. Bulk-editing objects in this way can be instrumental in saving time. The process involves first...