Schedule Statistics

NetPoint tracks a number of statistics for each plan, such as the number of activities, types of links, and float distributions.

Viewing Reports

To view a schedule’s statistics, click Schedule > View Statistics… from the menu bar. The Schedule Statistics window opens with the following information:

schedule statistics dialog

Activity Count
Number of activities in the schedule.
Link Count
Number of links in the schedule.
Start Embeds
Number of start embeds in the schedule.
Finish Embeds
Number of finish embeds in the schedule.
Zero-gap Links
Number of zero-gap links in the schedule.
Project Duration in Calendar Periods
Number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) between the project start and project completion, including holidays, non-working periods, and weekends.
Project Duration in Work Periods
Number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) between the project start and project completion, excluding holidays, non-working periods, and weekends (based on whichever calendar has been selected as default).
Longest Path in Calendar Periods
The chain of linked objects that lasts the most number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) including holidays, non-working periods, and weekends.
Longest Path in Work Periods
The chain of linked objects that lasts the most number of days (or, if PolyTime is enabled, number of minutes, hours, etc.) excluding holidays, non-working periods, and weekends.
Hard-Link Count
Number of hard links in the schedule.
Soft-Link Count
Number of soft links in the schedule.
Resource-Link Count
Number of resource links in the schedule.
External-Link Count
Number of external links in the schedule.
Contractual-Link Count
Number of contractual links in the schedule.
Float Distributions
The percentile rank for different float values.