Answer
NetPoint will import and export to Primavera P6 versions 6.0, 6.1, 6.2, and 7.0. The user must have administrative privileges and the Primavera Integration API must be installed. Before importing a schedule from P6 to NetPoint, the project must be scheduled in P6 (by pressing the F9 key or selecting from the menu bar). Otherwise, the import process may terminate abnormally or imported dates may become corrupted.