When importing from P6, why are my dates incorrect?

Answer

NetPoint® will import and export to Primavera P6 versions 6.0, 6.1, 6.2, and 7.0. The user must have administrative privileges and the Primavera Integration API must be installed. Before importing a schedule from P6 to NetPoint, the project must be scheduled in P6 (by pressing the F9 key or selecting Tools > Schedule from the menu bar). Otherwise, the import process may terminate abnormally or imported dates may become corrupted.